The R package ganttrify is really suitable for Gantt chart, all we need to do is to compile the time schedual into a csv file, then read it into R, then apply the ganttrify function to plot it.
So initially I prepared a CSV file with my Google Sheets, then pasted it into a csv file, then read it and tyde it a bit with kable function.
> Gantt <- read.csv("./Gantt.csv",sep="\t")
> knitr::kable(Gantt)
|wp |index |activity |start_date |end_date |
|:----------------------------|:-----|:----------------------------------|:----------|:----------|
|Systematic literature review |1.1 |analysis of papers |01/10/2020 |31/12/2020 |
|Systematic literature review |1.1.1 |thematic analysis |01/10/2020 |30/11/2020 |
|Systematic literature review |1.1.2 |method analysis |01/12/2020 |31/12/2020 |
|Systematic literature review |1.2 |discussions |01/01/2021 |31/01/2021 |
|Systematic literature review |1.2.1 |limitations |01/01/2021 |15/01/2021 |
|Systematic literature review |1.2.2 |future directions |16/01/2021 |31/01/2021 |
|Systematic literature review |1.3 |draft review |01/02/2021 |30/04/2021 |
|Slow Delivery |2.1 |survey |01/10/2020 |31/07/2021 |
|Slow Delivery |2.1.1 |survey design |01/10/2020 |31/12/2020 |
|Slow Delivery |2.1.2 |data collection from survey launch |01/01/2021 |31/01/2021 |
|Slow Delivery |2.1.3 |data analysis |01/02/2021 |30/04/2021 |
|Slow Delivery |2.1.4 |draft the paper |01/05/2021 |31/07/2021 |
|Slow Delivery |2.2 |interview with industrial staff |01/08/2021 |30/09/2022 |
|Slow Delivery |2.2.1 |interview conducting |01/08/2021 |30/11/2021 |
|Slow Delivery |2.2.2 |coding from interview |01/12/2021 |28/02/2022 |
|Slow Delivery |2.2.3 |Simulation Work |01/03/2022 |30/06/2022 |
|Slow Delivery |2.2.4 |draft paper |01/07/2022 |30/09/2022 |Note that the time format is not correct, it should be like 2020-02-01 format. So I changed is, also, the wp,activity, start_date, and end_date are 4 default columns, I just want to keep that, so I decide to paste the index with the activity column. After I done these actions, I can directly apply ganttrify function to draw the plot. The total code is below. Honestly, if I previously orgnise the excel table better, everything could be even simpler.
library("ganttrify")
Gantt <- read.csv("./Gantt.csv",sep="\t")
Gantt$start_date <- sapply(Gantt$start_date, function(x) paste(rev(strsplit(x,split="/")[[1]]),collapse='-'))
Gantt$end_date <- sapply(Gantt$end_date, function(x) paste(rev(strsplit(x,split="/")[[1]]),collapse='-'))
Gantt$activity <- paste(Gantt$index, Gantt$activity)
ganttrify(project = Gantt,
by_date = TRUE,
size_text_relative = 1.1,
mark_quarters = TRUE,
month_number = TRUE,
font_family = "Roboto Condensed")